    Installation procedure of engineering rig

    Release time:2019-5-28    This article is read 1004 second

    The supporting installation of the rotary plate drive device before leaving the factory has been found to be correct. When installing on site, it is enough to check whether the surface of the rotary plate beam lug plate hole

    Installation procedure of engineering rig

    The supporting installation of the rotary plate drive device before leaving the factory has been found to be correct. When installing on site, it is enough to check whether the surface of the rotary plate beam lug plate hole, base corresponding connection hole and connection pin shaft are clean or not. When no unsafe factors are identified, lift the rotary drive device into the installation position as a whole

    Installation procedure of engineering rig

    1. Install the base: position the left and right front base in accordance with the painted line on the foundation so that

    The engineering drilling machine

    The borehole signs on the left and right front base are aligned with the parallel eye centerline.

    2. Install rotary drive device:

    The engineering drilling machine

    The supporting installation of the rotary plate drive device before leaving the factory has been found to be correct. When installing on site, it is enough to check whether the surface of the rotary plate beam lug plate hole, base corresponding connection hole and connection pin shaft are clean or not. When no unsafe factors are identified, lift the rotary drive device into the installation position as a whole and insert 8 connecting pin shafts. When inserting pin shafts, pay attention to the lateral direction of the well head to the center of the well head and lock pin shafts with pins respectively.

    3. Installation of engineering rig winch: the winch has been properly aligned when installed before delivery, and a positioning block is welded at the corresponding position of the rig base. During site installation, hoist the winch onto the winch beam of the base. After positioning according to the positioning block, use the fastening bolt M36*120 to fix the winch base and the rig base.

    工程钻机的安装步骤

    4. Install the moving position of engineering drilling rig guide rail and blowout preventer: see the operation manual of engineering drilling rig base for specific installation steps.

    5. Derrick installation: install the derrick according to the instruction manual (note: the casing platform and fast rope arrangement device shall be installed after the derrick is erected).

    6. Crane installation: first lift the crane to the top of the derrick, insert the locating pin on the top of the derrick into the locating pin hole on the derrick, and then connect it with M30 bolts. Crane accessories, such as auxiliary pulley, trussed crane should be fully installed.

    7. Install the trolley and hook, and tie the lifting rope, engineering drilling rope of the crane and the trolley (the way of threading is straight threading), and hang the tripod for lifting.


    Installation procedure of engineering rig
    The last one:Hoisting machine type 50 drilling rigNext item:Hoisting machine type 50 drilling rig

    400-0537-369

    Shandong xiongtai machinery group co. LTD
    National free sales hotline: 400-0537-369
    Seat: 0537-2339569 
    Fax: 0537-2339569
    WeChat: 15905372283
    Email address: xiongtaijx@163.com
    Address: shuyuan industrial park, qufu city, jining city, shandong province

    Mobile Station

    Copyright:Shandong xiongtai machinery group co., ltd. All rights reserved      Lu ICP 19020630 -1   公示信息